Aboitiz Power Corp. is moving to take full ownership of the 420-megawatt Pagbilao Unit 3 coal-fired power plant in Quezon province through a P6.12-billion acquisition of its joint venture partner’s stake, consolidating control of the facility under its wholly owned subsidiary.
Therma Power Inc. (TPI), an AboitizPower subsidiary, has signed a share purchase agreement to acquire all 447.83 million outstanding shares of TPEC Holdings Corp. (TPEC HoldCo) from TeaM (Philippines) Energy Corp. (TPEC) for a cash consideration of P6.12 billion.
The shares comprise 900,000 common shares and 446.9 million preferred shares, with the transaction covering 100 percent of TPEC HoldCo’s outstanding capital stock.
TPEC HoldCo currently owns half of Pagbilao Energy Corp. (PEC), which owns and operates the 420-MW power plant in Pagbilao, Quezon. TPI owns the other half, making the two companies equal partners in the facility.
Upon completion of the acquisition, TPI will directly and indirectly own 100 percent of PEC, with both TPEC HoldCo and PEC becoming wholly owned subsidiaries of TPI. Their financial results will subsequently be fully consolidated into AboitizPower’s financial statements.
The transaction remains subject to approval by the Philippine Competition Commission and other customary closing conditions.
The TPI board of directors authorized the execution of the share purchase agreement during a meeting on November 13, 2026.
The acquisition will give AboitizPower full ownership and operational control of another major generating asset, removing the existing joint venture arrangement and allowing the company to consolidate the plant’s earnings and financial position.
The deal also deepens the group’s exposure to coal-fired generation even as the power industry navigates the transition toward cleaner energy sources and the need to maintain reliable electricity supply.